Helicopter operations began in late July to support the next phase of work to raise the electric transmission lines spanning the St. Johns River near JAXPORT’s Blount Island terminal.
The project, led by JEA in partnership with the Florida Department of Transportation, the City of Jacksonville and JAXPORT, is increasing the transmission lines from their current height of 185 feet to 225 feet, providing 205 feet of operational clearance, supporting the continued growth of international container trade in Jacksonville and the 15,000 regional jobs it sustains.
Here’s what leaders are saying about the milestone.
“Strong partnerships and investments in critical infrastructure are key to keeping Florida competitive. FDOT’s investment in this project will help strengthen JAXPORT’s ability to serve a growing global market and support the efficient movement of goods through one of our state’s most important trade gateways.” – Florida Department of Transportation Secretary Jared W. Perdue, P.E.
“As this vital project reaches a new milestone, the City of Jacksonville’s investment will create jobs, attract new businesses, and continue growing our port that is already a global leader in trade. We are grateful for the partnership with JAXPORT, JEA and the State of Florida.” – Jacksonville Mayor Donna Deegan
“Every investment in our fast-growing port is an investment in jobs for Jacksonville. By raising the power lines to accommodate larger ships, JAXPORT and JEA are accelerating international trade, growing our City’s economy, and creating more opportunities for Jacksonville businesses and families.” – Jacksonville City Council President Nick Howland
“The community and I of District 2 are pleased to see this project moving forward on schedule. We look forward to the projects completion as it will open new opportunities for more jobs and help provide sustainability for the future of our city.” – Councilman Mike Gay, District 2
On July 30, crews began using helicopters to place guide lines through pulleys on the new transmission towers spanning the St. Johns River.
These guide lines will help crews safely pull the new electrical wires into place.
Helicopter-supported work will continue over the next several months as JEA completes the installation across the river.
Once complete, the raised transmission lines will provide the additional clearance larger ships need to safely navigate the river’s 47-foot-deep shipping channel to and from JAXPORT’s Blount Island Marine Terminal.